Stourport Bridge Refurbishment

Stourport Bridge

Stourport Bridge was built in 1870 by local contractor Thomas Vale Construction.

START DATE 23RD OCTOBER 2006

Foreword

Overview of the scheme

Traffic Managment

Essential Contacts

Have your say...

Key Challenges Faced

Project Programme

Early signs fo the finished product

Overview of the scheme ……

The intentions of the refurbishment scheme are to:

  • relocate the services currently in the footway to the underside of the bridge
  • remove the surfacing and the granular fill between the structural elements to permit the application of a protective coating and the casting of a new reinforced concrete slab
  • provide a waterproofing membrane to prevent the ingress of water into the structure which has previously caused the unsightly staining to paint finish
  • repair and replace defective decorative castings
  • install heritage style cast iron kerbing to protect pedestrians and prevent vehicles impacting on the decorative parapet fencing
  • resurface the carriageway from the junction with the sports centre through to the junction with York Street, High Street, and New Street
  • paint the entire structure to include the spiral staircase, lighting columns and parapets.

Traffic management…………

In order to undertake the work it is necessary to restrict the carriageway over the bridge to one lane.

Traffic will be managed by a controller normally present at junctions with permanent traffic signals. This will allow the flexibility to manage the tidal traffic flows that exist eastbound in the morning and westbound in the evening. The aspiration is to try and  keep Stourport running as near normal as is possible during the works.

There will be a total weekend closure from the 3rd - 5th August 2007 to allow the resurfacing work to be undertaken.

Emergency Service vehicles will be allowed full access through the works at all times.

In order to relieve the town of unnecessary traffic during the essential works signing will be in place to encourage drivers on through-journeys to choose alternative routes.

Greater enforcement of parking will also be made by West Mercia Police to keep the towns traffic flowing smoothly.

Business as usual in Stourport throughout the works

Have your Say on the Colour Scheme for the Refurbishment………

Thank you everyone who recorded their choice for the colour scheme.

Out of the four options:

  1. Dark Blue/Light Blue
  2. Dark Blue and Gold
  3. Green/Cream
  4. Slate Grey/Cream/Gold

the most popular was Dark Blue and Gold.

Final colour for Stourport Bridge

Project Programme

21st May 2007

Switch over to pahse 3 (downstream half of bridge)

2nd August 2007

Completion of the deck and paraet works

3rd-5th August 2007

Weekend closure to complete surfacing and road markings

By 10th August 2007

Road open to two-way traffic

October 2007

Fitting of new roundels and competion of painting

Early signs of the finished product

Upstream Parapet before

Upsteam Parapet before (above) and after (below)

Final colour for Stourport Bridge

Newly painted parapet protect, and halfdeck waiting for waterproofing membrane to be applied.

Newly painted parapet

Bridge Deck part waterproofed

Bridge Deck part waterproofed

Page Information:
Last modification: 08:07:16, 07th June, 2007 by Lucy Dean
Review date: 04th September, 2007
Select English Language Select Bengali Language Select Cantonese Language Select Polish Language Select Portuguese Language Select Spanish Language Select Turkish Language Select Urdu Language
©2008 Worcestershire Hub. All rights reserved.
Disclaimer | Privacy Statement | Service Standards | Help
Your feedback is essential:
Page Comments?